  1. X does 1/4th of a job in 6 days. Y completes rest of the job in 12 days. In how many days could X and Y together have completed the job?

Options:
A .  \(6\frac{3}{5}days\)
B .  \(7\frac{3}{5}days\)
C .  \(8\frac{3}{5}days\)
D .  \(9\frac{3}{5}days\)
Answer: Option D