Question
Which of the following is not a use of the PDCA cycle?
Options:
A .  Starting a new project aimed at improvement
B .  For continuous improvement
C .  As a project planning tool
D .  For intermittent improvement
Answer: Option D
Answer: (d).For intermittent improvement