When the TWC lies below the JHC at all discharges, the problem can be solved by which of the following provisions?
i. Constructing a sloping apron above the river bed
ii. Provision of roller bucket type of energy dissipator
iii. Provision of a ski-jump bucket
iv. A sloping apron below the river bed
v. Construction of a subsidiary dam
vi. A sloping apron partly above and partly below the river bed
Options:
A .  i, iii and v
B .  i, ii and vi
C .  iii, iv and v
D .  i, iii, iv and v
Answer: Option C
Answer: (c).iii, iv and v