Sail E0 Webinar
Question

The “turn-around” time of a user job is the


Options:
A .  time since its submission to the time its results become available.
B .  time duration for which the CPU is allotted to the job.
C .  total time taken to execute the job.
D .  time taken for the job to move from assembly phase to completion phase.
Answer: Option C




Submit Your Solution Below and Earn Points !