Select the incorrect statement.
Options:
A .  The progress of work in low level method of mound construction is very slow
B .  Barge method of mound construction is economical
C .  In low level method of mound construction, the area of working is limited
D .  In staging method of mound construction, the work is not interrupted even during stormy weather
Answer: Option B