Sail E0 Webinar
Question
Pick up the correct statement. dummy activity on a pert/cpm chart means, it
Options:
A .   Consumes time, but no resources
B .   Consumes resources but no time
C .   Consumes neither time nor resources
D .   Is a dangling event
Answer: Option C
Explanation :

Was this answer helpful ?
Next Question

Submit Solution