In time-cost optimization of a project, crashing is done.
Options:
A .  On all the activities
B .  On all the activities lying on the critical path
C .  Only on activities lying on the original critical path and having flatter cost slopes
D .  On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Answer: Option D