Sail E0 Webinar
Question
In Material Requirement Planning
Options:
A .  Material availability is ensured
B .  If shortage exists the corresponding elements are planned
C .  Stock transfers are also possible
D .  The availability of the components is ensured via dependent requirements
Answer: Option D





Submit Your Solution Below and Earn Points !
Next Question

Submit Solution