If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is


Options:
A .  `(a + m + b)/(6)`
B .  `(a + 2m + b)/(6)`
C .  `(a + 4m + b)/(6)`
D .  `(a + 5m + b)/(6)`
Answer: Option C