If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
Options:
A .  (a + m + b)/6
B .  (a + 2m + b)/6
C .  (a + 4m + b)/6
D .  (a + 5m + b)/6
Answer: Option C