Question
If 17 labourers can dig a ditch 26 m long in 18 days, working 8 hours a day; how many more labourers should be engaged to dig a similar ditch 39 m long in 6 days, each labourer working 9 hours a day ?
Answer: Option B
Submit Your Solution Below and Earn Points !