Question
A contract is to be complete in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, $$\frac{4}{7}{\text{ }}$$ of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?
Answer: Option B
Submit Your Solution Below and Earn Points !
Submit Your Solution Below and Earn Points !
Submit Solution