Cost and schedule are a part of_________________________?
Options:
A .  Product Metrics
B .  Process Metrics
C .  Project Metrics
D .  All of the mentioned
Answer: Option C
PROJECT METRICS DESCRIBE THE PROJECT CHARACTERISTICS AND EXECUTION