Question
An efficiency variance is 200 units and the actual input quantity is 500 units, then the budgeted input quantity will be
Answer: Option A
Answer: (a).300 units
Was this answer helpful ?
Answer: (a).300 units
Was this answer helpful ?
Submit Solution