Question
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
Answer: Option A
Was this answer helpful ?
Ratio of rates of working of A and B = 2 : 1.
So, ratio of times taken = 1 : 2.
B's 1 day's work = \(\frac{1}{12}\)
So, A's 1 day's work = \(\frac{1}{6}\) ; (2 times of B's work)
(A + B)'s 1 day's work = \(\left(\frac{1}{6}+\frac{1}{12}\right)=\frac{3}{12}=\frac{1}{4}.\)
So, A and B together can finish the work in 4 days.
Was this answer helpful ?
Submit Solution