A pert network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. the probability that the project will be completed in 20 days is
Options:
A .   0.50
B .   0.66
C .   0.84
D .   0.95
Answer: Option C
Explanation :