A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?
Options:
A .  1.0 hour per unit
B .  1.2 hours per unit
C .  1.4 hours per unit
D .  1.6 hours per unit
Answer: Option A