A clay sample 24mm thick takes 20 minutes to consolidate 50% with single drainage. The field clay layer from which sample was obtained takes 386 days to consolidate 50% with double drainage. Find the depth of the clay layer in the field.
Options:
A .  800cm
B .  500cm
C .  600cm
D .  480cm
Answer: Option A
Answer: (a).800cm