For a foundation, find the elapsed time in which 10% of ultimate settlement will occur. The coefficient of consolidation is 4*10¯⁴cm²/s. The average drainage path is 50cm.
Options:
A .  19.9 hours
B .  15.5 hours
C .  13.9 hours
D .  17.5 hours
Answer: Option C
Answer: (c).13.9 hours