Sail E0 Webinar
Question
24 men can complete a work in 20 days. How many more men are required to complete the work in 12 days?
Options:
A .  40
B .  12
C .  16
D .  18
Answer: Option C
:
C
Method 1:Using man-days
Amount of work in terms of man days =24×20=480 man days
So, number of men required to complete the work in 12 days =48012=40men.
16 more men are required. Hence option (c)
Method 2: Using constant product rule
Decrease in number of days =1(208)=12.5
Increase in number of men =11.5=16 men to finish the same work.

Was this answer helpful ?
Next Question

Submit Solution

Your email address will not be published. Required fields are marked *

More Questions on This Topic :


Latest Videos

Latest Test Papers