___ is an empty exercise without controlling because, in the absence of a control system, it is impossible to monitor the progress and keep a check on the proper implementation of plans.


Options:
A .   Coordinating
B .   Directing
C .   Planning
D .   Staffing
Answer: Option C
:
C

Planning is an empty exercise without controlling because, in the absence of a control system, it is impossible to monitor the progress and keep a check on the proper implementation of plans.