Popular Courses
Sail E0 Package
Valid Till Next Exam
Fast Math Tricks
165 videos
Quantitative Aptitude
645 Videos
Reasoning Aptitude
161 Videos
CLASS 8 MATHS(CBSE)
417 Videos
CLASS 9 MATHS(CBSE)
40 hours, 647 questions
Check All Courses
Resources
Store
Blog
More
About Us
Contact Us
Register / Login
Menu
Home
Blog
Store
About Us
Contact Us
Profile Settings
Attempted Tests
My Purchases
Popular Courses
Sail E0 Package
Valid Till Next Exam
Fast Math Tricks
165 videos
Quantitative Aptitude
645 Videos
Reasoning Aptitude
161 Videos
CLASS 8 MATHS(CBSE)
417 Videos
CLASS 9 MATHS(CBSE)
40 hours, 647 questions
Check All Courses
Search
Search
Home
Topics
MCQs
Total Questions : 25 | Page
1
of 3 pages
Question 1.
After MRP run, which of the following gets created in Planning?
Production Order & Planned Order
Purchase Order
None of the above
Scheduling Lines
See Solution
Discuss Question
Answer: Option A. ->
Production Order & Planned Order
Question 2.
What are the reports generated in product cost controlling information system?
Product cost planning
Cost object controlling with the subcomponents
Actual Costing / Material Ledger
All of these
See Solution
Discuss Question
Answer: Option D. ->
All of these
Question 3.
In Material Requirement Planning
Material availability is ensured
If shortage exists the corresponding elements are planned
Stock transfers are also possible
The availability of the components is ensured via dependent requirements
See Solution
Discuss Question
Answer: Option D. ->
The availability of the components is ensured via dependent requirements
Question 4.
Planning can create the following after MRP run
Planned Orders
Production Orders
Purchase Orders
Schedule Lines
See Solution
Discuss Question
Answer: Option A. ->
Planned Orders
Question 5.
Settlement in product cost controller is based on
Period-oriented
Costs of the product cost controller
Order settlement
No settlement rule
See Solution
Discuss Question
Answer: Option A. ->
Period-oriented
Question 6.
A purchasing group is a sub-set of a purchasing organization?
Yes
No
All of these
None
See Solution
Discuss Question
Answer: Option A. ->
Yes
Question 7.
BOMs are always created as
Single Level
Multi-Level
Components
Along with routings
See Solution
Discuss Question
Answer: Option A. ->
Single Level
Question 8.
Where can you define the valid receivers for production order costs?
In the valuation variant
In the production scheduling profile
In the settlement profile
In the costing variant
See Solution
Discuss Question
Answer: Option B. ->
In the production scheduling profile
Question 9.
What are the production process in SAP?
Discrete Manufacturing
Repetitive Manufacturing
Production- Process Industries
All of these
See Solution
Discuss Question
Answer: Option D. ->
All of these
Question 10.
In Material Requirement Planning
Material availability is ensured
If a shortage exists the corresponding elements are planned
Stock transfers are also possible
The availability of the components is ensured via dependent requirements
See Solution
Discuss Question
Answer: Option D. ->
The availability of the components is ensured via dependent requirements
1
2
3
Next →
Share this page with your friends!
Share this page with your friends!
Latest Videos
Chapter 1 - GLOBAL STEEL SCENARIO & INDI
Part 1 : (13-04-2024)
INDUSTRY AND COMPANY AWARENESS (ICA)
Direction Sense Test
Part 1
Reasoning (Hindi)
Chapter 1 - RMHP / OHP / OB & BP
Part 1 : (14-02-2024)
GPOE 2024
Cube & Cuboid
Part 1
Reasoning (Hindi)
Data Interpretation (DI)
Basic Concept
Reasoning (Hindi)
Counting Figures Part 1
Counting Of Straight Lines
Reasoning (Hindi)
Sail E0 free webinar
Webinars
Real Numbers
Part 7
Class 10 Maths
Real Numbers
Part 1
Class 10 Maths
Polynomials
Part 1
Class 10 Maths
Latest Test Papers
Chapter 1.1 : INTRODUCTION
Chapter 1 : Raw Material Handling Plant
GPOE/GPA 2024
Chapter 1.1 : Personnel Functions- An ov
Chapter 1 : Personnel Management
GFM 2024
Chapter 3.1 : INTRODUCTION
Chapter 3 : Sinter Plant
GPOE/GPA 2024
Chapter 2.3 : COAL HANDLING PLANT - Set
Chapter 2 : Coke Ovens and Coal Chemicals
GPOE/GPA 2024
Chapter 2.1 : Overview
Chapter 2 : Materials Management
GFM 2024