Question 51. While scheduling a project by C.P.M.
  1.    A project is divided into various activities
  2.    Required time for each activity is established
  3.    Net work is drawn by connecting the activities and the events
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 52. Final technical authority of a project lies with
  1.    Assistant Engineer
  2.    Executive Engineer
  3.    Superintending Engineer
  4.    Chief Engineer
 Discuss Question
Answer: Option D. -> Chief Engineer
Question 53. The technique for establishing and maintaining priorities among the various jobs of a project, is known
  1.    Event flow scheduling technique
  2.    Critical ratio scheduling
  3.    Slotting technique for scheduling
  4.    Short interval scheduling
 Discuss Question
Answer: Option B. -> Critical ratio scheduling
Question 54. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
  1.    Started 5 days later
  2.    Completed 5 days later
  3.    Performed at slower rate in 15 days
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 55. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
  1.    20
  2.    25
  3.    35
  4.    15
 Discuss Question
Answer: Option B. -> 25
Question 56. The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
  1.    19
  2.    14
  3.    24
  4.    None of these
 Discuss Question
Answer: Option A. -> 19
Question 57. Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
  1.    Ice
  2.    Concrete
  3.    Loose sand
  4.    Earth
 Discuss Question
Answer: Option D. -> Earth
Question 58. Which one of the following represents an event?
  1.    Concrete cured
  2.    Fixing of door
  3.    Plastering of walls
  4.    Selecting sites
 Discuss Question
Answer: Option A. -> Concrete cured
Question 59. The reduction in project time normally results in
  1.    Decreasing the direct cost and increasing indirect cost
  2.    Increasing the direct cost and decreasing the indirect cost
  3.    Increasing the direct cost and indirect cost both
  4.    Decreasing the direct cost and indirect cost both
 Discuss Question
Answer: Option B. -> Increasing the direct cost and decreasing the indirect cost
Question 60. In the given figure, the network of a project represents
  1.    Activity of an excavation of a footing
  2.    Activity of an excavation which starts at event No. 1 and ends at even No. 2
  3.    Activity of excavation which takes 8 units of time
  4.    None of these
 Discuss Question
Answer: Option C. -> Activity of excavation which takes 8 units of time