Question 421. While scheduling a project by C.P.M.
  1.    Net work is drawn by connecting the activities and the events
  2.    Required time for each activity is established
  3.    All listed here
  4.    A project is divided into various activities
 Discuss Question
Answer: Option C. -> All listed here
Question 422. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
  1.    25
  2.    20
  3.    15
  4.    35
 Discuss Question
Answer: Option A. -> 25
Question 423. The technique for establishing and maintaining priorities among the various jobs of a project, is known
  1.    Event flow scheduling technique
  2.    Short interval scheduling
  3.    Slotting technique for scheduling
  4.    Critical ratio scheduling
 Discuss Question
Answer: Option D. -> Critical ratio scheduling
Question 424. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
  1.    Performed at slower rate in 15 days
  2.    Started 5 days later
  3.    All listed here
  4.    Completed 5 days later
 Discuss Question
Answer: Option C. -> All listed here
Question 425. Final technical authority of a project lies with
  1.    Executive Engineer
  2.    Assistant Engineer
  3.    Superintending Engineer
  4.    Chief Engineer
 Discuss Question
Answer: Option D. -> Chief Engineer
Question 426. Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
  1.    Loose sand
  2.    Ice
  3.    Concrete
  4.    Earth
 Discuss Question
Answer: Option D. -> Earth
Question 427. The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
  1.    19
  2.    14
  3.    None of these
  4.    24
 Discuss Question
Answer: Option A. -> 19
Question 428. In the given figure, the network of a project represents
  1.    None of these
  2.    Activity of an excavation which starts at event No. 1 and ends at even No. 2
  3.    Activity of excavation which takes 8 units of time
  4.    Activity of an excavation of a footing
 Discuss Question
Answer: Option C. -> Activity of excavation which takes 8 units of time
Question 429. The reduction in project time normally results in
  1.    Increasing the direct cost and indirect cost both
  2.    Decreasing the direct cost and increasing indirect cost
  3.    Decreasing the direct cost and indirect cost both
  4.    Increasing the direct cost and decreasing the indirect cost
 Discuss Question
Answer: Option D. -> Increasing the direct cost and decreasing the indirect cost
Question 430. Which one of the following represents an event?
  1.    Selecting sites
  2.    Fixing of door
  3.    Plastering of walls
  4.    Concrete cured
 Discuss Question
Answer: Option D. -> Concrete cured