  1. A and B working alone can finish a piece of work in 8 and 7 days respectively. If they work at it alternately for a day, A beginning, in how many days will the work be finished?

Options:
A .  \(6\frac{1}{2}days\)
B .  7 days
C .  \(7\frac{1}{2}days\)
D .  8 days
Answer: Option C