The essential condition for the decompression of an activity is that
Options:
A .  An activity could be decompressed to the maximum extent of its normal time
B .  The project time should change due to decompression
C .  After decompression the time of an activity invariably exceeds its normal time
D .  An activity could be decompressed to the maximum extent of its normal time
Answer: Option D