Free float for any activity is defined as the difference between
Options:
A .  its earliest finish time and earliest start time for its successor activity
B .  its latest start time and earliest start time
C .  its latest finish time and earliest start time for its successor activity
D .  its earliest finish time and latest start time for its successor activity
Answer: Option A