Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float
Options:
A .  1 and 4 are correct
B .  2 and 3 are correct
C .  1 and 4 are correct
D .  1 and 2 are correct
Answer: Option B