1. If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
Options:
A .  Latest start time ? earliest start time
B .  Latest finish time ? earliest finish time (EFT)
C .  TL?EFT
D .  All of the above
Answer: Option D