4. Pick up the correct statement from the following
Options:
A .  The float may be positive, zero or negative
B .  All of the above.
C .  If the float of an activity is negative, delay in its performance is bound to delay the completion of project
D .  If the float of an activity is zero, the activity is critical and any aelay in its performance will delay the whole project
Answer: Option B