Sail E0 Webinar
Question
18 men can complete a piece of work in 63 days. 9 women take 189 days to complete the same piece of work. How many days will 4 men, 9 women and 12 children together take to complete the piece of work if 7 children alone can complete the piece of work in 486 days ?
Options:
A .  54 days
B .  63 days
C .  76 days
D .  81 days
E .  None of these
Answer: Option D