Sail E0 Webinar

MCQs

Total Questions : 192 | Page 13 of 20 pages
Question 121. Which of the following depicts the correct order of the stages involved in grid integration of wind energy?
  1.    System operations → physical connection → planning
  2.    Planning → system operations → physical connection
  3.    Planning → physical connection → system operations
  4.    Physical connection → planning → system operations
 Discuss Question
Answer: Option C. -> Planning → physical connection → system operations
Answer: (c).Planning → physical connection → system operations
Question 122. What are the two types of planning activities related to grid integration?
  1.    Network-wide and project-specific
  2.    BJT and MOSFET
  3.    Rotor and shaft
  4.    Low power and high power designs
 Discuss Question
Answer: Option A. -> Network-wide and project-specific
Answer: (a).Network-wide and project-specific
Question 123. Network-wide plans in wind energy grid integration include _______
  1.    system impact studies done for a specific wind project
  2.    materials used to manufacture wind turbine blades
  3.    developing grid code
  4.    solar panel manufacturing plant
 Discuss Question
Answer: Option C. -> developing grid code
Answer: (c).developing grid code
Question 124. Which of the following best describes network-wide planning activity in grid integration?
  1.    Planning activities related to a unique wind project
  2.    Planning activities for all the future wind power plants
  3.    Planning activities for a telecommunication system
  4.    Planning activities for the maintenance of the existing wind power plants
 Discuss Question
Answer: Option B. -> Planning activities for all the future wind power plants
Answer: (b).Planning activities for all the future wind power plants
Question 125. What is project specific planning in wind energy grid integration?
  1.    Planning activities for a solar panel system
  2.    Planning activities for all the future wind power plants
  3.    Planning activities related to a unique wind project
  4.    Planning activities for the maintenance of the existing thermal power plants
 Discuss Question
Answer: Option C. -> Planning activities related to a unique wind project
Answer: (c).Planning activities related to a unique wind project
Question 126. In a substation, the wind power plant line is connected to a _______ voltage bus bar.
  1.    high
  2.    low
  3.    mini
  4.    medium
 Discuss Question
Answer: Option D. -> medium
Answer: (d).medium
Question 127. Which of the following are a few primary tests performed after commissioning phase in the physical connection stage?
  1.    Switch-gear functioning and quality parameters
  2.    Feathering
  3.    Wind turbine blade tests
  4.    Rotor and shaft tests
 Discuss Question
Answer: Option A. -> Switch-gear functioning and quality parameters
Answer: (a).Switch-gear functioning and quality parameters
Question 128. What is a grid code for wind energy integration?
  1.    A binary code
  2.    A hexadecimal code
  3.    A code of conduct
  4.    A rulebook specifying generator properties
 Discuss Question
Answer: Option D. -> A rulebook specifying generator properties
Answer: (d).A rulebook specifying generator properties
Question 129. Which of the following is/are good practices for grid integration of wind power plant?
  1.    Day-ahead unit commitment process
  2.    Day-ahead unit commitment process, economic dispatch process
  3.    Optimized transmission from resources-rich areas to load, flexible generation
  4.    Rotor and shaft tests
 Discuss Question
Answer: Option C. -> Optimized transmission from resources-rich areas to load, flexible generation
Answer: (c).Optimized transmission from resources-rich areas to load, flexible generation
Question 130. Which of the following are impacts of grid integration of wind power plant?
  1.    Day-ahead unit commitment process
  2.    Day-ahead unit commitment process, economic dispatch process
  3.    Generator types
  4.    Rotor and shaft tests
 Discuss Question
Answer: Option B. -> Day-ahead unit commitment process, economic dispatch process
Answer: (b).Day-ahead unit commitment process, economic dispatch process

Latest Videos

Latest Test Papers