Question 11. TPM ensures an improved return on investment.
  1.    True
  2.    False
  3.    May be True or False
  4.    Can't say
 Discuss Question
Answer: Option A. -> True
Answer: (a).True
Question 12. Which of the following is not an advantage of implementing TPM?
  1.    Improved equipment reliability
  2.    Reduced equipment downtime
  3.    Increased equipment downtime
  4.    Lower maintenance and production costs
 Discuss Question
Answer: Option C. -> Increased equipment downtime
Answer: (c).Increased equipment downtime
Question 13. Which of the following is not an advantage of implementing TPM?
  1.    Enhanced job satisfaction
  2.    Zero defects
  3.    Improved teamwork between operators and maintenance team
  4.    A decrease in equipment reliability
 Discuss Question
Answer: Option D. -> A decrease in equipment reliability
Answer: (d).A decrease in equipment reliability
Question 14. Which of the following is not a type of loss examined by TPM?
  1.    Down-time loss
  2.    Speed loss
  3.    Defect loss
  4.    Forecasting loss
 Discuss Question
Answer: Option D. -> Forecasting loss
Answer: (d).Forecasting loss
Question 15. TQM focuses on achieving autonomous maintenance.
  1.    True
  2.    False
  3.    May be True or False
  4.    Can't say
 Discuss Question
Answer: Option A. -> True
Answer: (a).True
Question 16. MP in Total Productive Maintenance refers to ______
  1.    Main program
  2.    Main part
  3.    Maintenance prevention
  4.    Major part
 Discuss Question
Answer: Option C. -> Maintenance prevention
Answer: (c).Maintenance prevention
Question 17. Breakdowns lead to long interruptions.
  1.    True
  2.    False
  3.    May be True or False
  4.    Can't say
 Discuss Question
Answer: Option A. -> True
Answer: (a).True
Question 18. Which of the following loss refers to the gradual deterioration in equipment cycle times?
  1.    Increased speed
  2.    Reduced speed
  3.    Maximum speed
  4.    Optimum speed
 Discuss Question
Answer: Option B. -> Reduced speed
Answer: (b).Reduced speed
Question 19. Which of the following is not a loss that TPM focuses on reducing?
  1.    Equipment breakdown
  2.    Defects and rework
  3.    Idling and minor stoppages
  4.    Optimized equipment cycle time
 Discuss Question
Answer: Option D. -> Optimized equipment cycle time
Answer: (d).Optimized equipment cycle time
Question 20. Which of the following is not a goal shared by TPM?
  1.    Zero defects
  2.    Maximum productivity
  3.    Minimum productivity
  4.    Zero breakdowns
 Discuss Question
Answer: Option C. -> Minimum productivity
Answer: (c).Minimum productivity