• [email protected]

Lakshya Education Lakshya Education

  • Home
  • Video Series
    • Vedic Maths Videos
    • Quantitative Aptitude Videos
    • Class 8 Maths Videos
    • Class 9 Maths Videos
    • Class 10 Maths Videos
  • Quiz Engine
  • Quiz & Solutions
  • Buy DVD Package
  • Blog
  • Login
  • Home
  • Topics
  • Engineering
  • Mechanical Engineering
  • Industrial Engineering And Production Management

Topics

  • 10th Grade
  • 11th And 12th
  • 11th Grade
  • 12th Grade
  • 4th Grade
  • 5th Grade
  • 6th Grade
  • 7th Grade
  • 8th Grade
  • 9th Grade
  • Cat
  • Commerce
  • Computer Science
  • Engineering
  • English
  • General Knowledge
  • Ias
  • Management
  • Quantitative Aptitude
  • Reasoning Aptitude

Industrial Engineering And Production Management Questions MCQs

Total Questions : 314

Page 1 of 16 pages
Question 1. Break-even analysis shows profit when
  1.    Sales revenue > total cost
  2.    Sales revenue = total cost
  3.    Sales revenue < total cost
  4.    Variable cost < fixed cost
Answer: Option A

Question 2. PERT analysis is based upon
  1.    Optimistic time
  2.    Pessimistic time
  3.    Most likely time
  4.    All of these
Answer: Option D

Question 3. The appellate authority for an industrial dispute is
  1.    Management
  2.    Labour court
  3.    High court/supreme court
  4.    Board of directors
Answer: Option C

Question 4. Pessimistic time is
  1.    The maximum time which an activity might require
  2.    The average time required for a job
  3.    The most probable time considering all conditions
  4.    The minimum time in which an activity can possibly be accomplished
Answer: Option A

Question 5. Choose the wrong statement. Motion study is used for
  1.    Improving a work method
  2.    Improvising a work method
  3.    Designing a work method
  4.    Reducing inventory costs
Answer: Option D

Question 6. The basic difference between PERT and CPM is that
  1.    PERT deals with events and CPM with activities
  2.    Critical path is determined in PERT only
  3.    Costs are considered on CPM only and not in PERT
  4.    Guessed times are used in PERT and evaluated times in CPM
Answer: Option D

Question 7. Value engineering aims at finding out the
  1.    Depreciation value of a product
  2.    Resale value of a product
  3.    Major function of the item and accomplishing the same at least cost without change in quality
  4.    Break-even point when machine requires change
Answer: Option C

Question 8. Product layout is employed for
  1.    Batch production
  2.    Continuous production
  3.    Effective utilization of machine
  4.    All of the above
Answer: Option B

Question 9. Process layout is employed for
  1.    Batch production
  2.    Continuous type of product
  3.    Effective utilization of machines
  4.    All of the above
Answer: Option A

Question 10. Bar chart is suitable for
  1.    Large project
  2.    Major work
  3.    Minor work
  4.    All of these
Answer: Option C

Question 11. Abbreviated work factor data is applied for
  1.    Material handling operation
  2.    Maintenance operation
  3.    Packing and shipping operation
  4.    All of these
Answer: Option D

Question 12. The type of layout used for manufacturing steam turbines, is
  1.    Product layout
  2.    Process layout
  3.    Fixed position layout
  4.    Any one of these
Answer: Option C

Question 13. The allowed time for a job equals standard time plus
  1.    Policy allowance
  2.    Interference allowance
  3.    Process allowance
  4.    Learning allowance
Answer: Option A

Question 14. The type of organisation preferred for a steel industry, is
  1.    Line organisation
  2.    Functional organisation
  3.    Line and staff organisation
  4.    Line, staff and functional organisation
Answer: Option D

Question 15. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
  1.    0.50
  2.    0.66
  3.    0.84
  4.    0.95
Answer: Option C

Question 16. The bonus increases in proportion to the increase in efficiency. This statement applies to
  1.    Halsey plan
  2.    Gantt plan
  3.    Emerson's efficiency plan
  4.    Rowan plan
Answer: Option C

Question 17. Critical path on PERT/CPM chart is obtained by joining the events having
  1.    Maximum slack
  2.    Minimum slack
  3.    Average slack
  4.    No slack
Answer: Option B

Question 18. Critical path method
  1.    Helps in ascertaining time schedules
  2.    Makes better and detailed planning possible
  3.    Provides a standard method for communicating project plans schedules and to time and cost performance
  4.    All of the above
Answer: Option D

Question 19. The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as
  1.    Duration
  2.    Total float
  3.    Free float
  4.    Interfering float
Answer: Option C

Question 20. The standard time for a job is
  1.    Total work content
  2.    Base time + relaxation time
  3.    Total work content + basic time
  4.    Total work content + delay contingency allowance
Answer: Option D

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • ...
  • 15
  • 16
  • Next →

Sub Topics

  • Automobile Engineering
  • Compressors Gas Turbines And Jet Engines
  • Engineering Drawing
  • Engineering Materials
  • Engineering Mechanics
  • Engineering Thermodynamics
  • Heat And Mass Transfer
  • Hydraulics And Fluid Mechanics
  • Industrial Engineering And Prod N Mgmt
  • Industrial Engineering And Production Management
  • Internal Combustion Engines I C Engines
  • Machine Design
  • Manufacturing And Production Technology
  • Power Plant Engineering
  • Refrigeration And Air Conditioning
  • Steam Boilers Engines Nozzles And Turbines
  • Strength Of Materials
  • Theory Of Machine
  • Workshop Technology

Recent Questions

What Does Braille Media Type Is Used For?....

Gunmetal And Bronze Are Not Corroded By The Action Of....

Provision For Doubtful Debts Account Is A/an....

The Prize That Is Awarded Every Two Years To People Who Have....

The Shoulder Provided Along The Road Edge Should Be....

How Much O₂ Can Be Obtained From 90 Kg Of Water?....

A Card Is Drawn At Random From A Pack Of 52 Cards. Find The ....

The Number Of Subordinates That Report Directly To A Single ....

A Petrol Engine Of A Car Develops 125 Nm Torque At 2700 R.p.....

Main Boring Diameter For Petroleum Well Is 20-30 Cms In Diam....

A Common Reason For Changing An Information System Is....

If The Kinetic Energy And Potential Energy Of A Simple Harmo....

An Athlete Claimed That His Timing For A 100 M Dash Should B....

Steady Flow Occurs When....

Who Founded The Amrit Bazar Patrika?....

Goosebumps Are Caused By Contractions Of The....

Choose The Word Which Is Different From The Rest.....

Which Of The Following Is The Educational Implication Of The....

A, B And C Start Running Simultaneously From Point P, Q And ....

Social Exclusion Denies Certain Individuals The ....

Lakshya Education
Lakshya Education
Chattisgarh,India
Email: [email protected]

Quick Links

  • Vedic Maths
  • Quantitative Aptitude
  • Class – IX Maths
  • Class – X Maths
  • YouTube Channel
  • Maths Fast Trick
  • Blog

Our Services

  • About us
  • Privacy
  • TOS
  • Contact
  • Copyright © 2022 All Right Reserved | Lakshya Education