Question 101. Gantt chart gives information about
  1.     Scheduling and routing
  2.     Sales
  3.     Production schedule
  4.     Machine utilization
 Discuss Question
Answer: Option C. ->  Production schedule
Explanation :
Question 102. Cpm has following time estimate
  1.     One time estimate
  2.     Two time estimate
  3.     Three time estimate
  4.     Four time estimate
 Discuss Question
Answer: Option A. ->  One time estimate
Explanation :
Question 103. Scheduling gives information about
  1.     When work should start and how much work should be completed during a certain period
  2.     When work should complete
  3.     That how idle time can be minimized
  4.     Proper utilization of machines
 Discuss Question
Answer: Option A. ->  When work should start and how much work should be completed during a certain period
Explanation :
Question 104. The two bin system is concerned with
  1.     Ordering procedure
  2.     Forecasting sales
  3.     Production planning
  4.     Despatching and expediting
 Discuss Question
Answer: Option A. ->  Ordering procedure
Explanation :
Question 105. Activity slack or float of any event on a pert/cpm chart is represented by
  1.     Latest start time of succeeding event earliest finish time of preceding event activity time
  2.     Latest start time of the event earliest start time of the event
  3.     Latest finish time of event earliest finish time of the event
  4.     Anyone of the above
 Discuss Question
Answer: Option D. ->  Anyone of the above
Explanation :
Question 106. Work study is concerned with
  1.     Improving present method and finding standard time
  2.     Motivation of workers
  3.     Improving production capability
  4.     Improving production planning and control
 Discuss Question
Answer: Option A. ->  Improving present method and finding standard time
Explanation :
Question 107. When slack of an activity is positive
  1.     It represents a situation where extra resources are available and the completion of project is not delayed
  2.     It represents that a programme falls behind schedule and additional resources are required to complete the project in time
  3.     The activity is critical and any delay in its performance will delay the completion of whole project
  4.     Any one of the above
 Discuss Question
Answer: Option A. ->  It represents a situation where extra resources are available and the completion of project is not delayed
Explanation :
Question 108. When slack of an activity is negative
  1.     It represents a situation where extra resources are available and the completion of project is not delayed
  2.     It represents that a programme falls behind schedule and additional resources are required to complete the project in time
  3.     The activity is critical and any delay in its performance will delay the completion of whole project
  4.     All of the above
 Discuss Question
Answer: Option B. ->  It represents that a programme falls behind schedule and additional resources are required to complete the project in time
Explanation :
Question 109. The time which results in the least possible direct cost of an activity is known as
  1.     Normal time
  2.     Slow time
  3.     Crash time
  4.     Standard time
 Discuss Question
Answer: Option B. ->  Slow time
Explanation :
Question 110. Tick the odd man out
  1.     Taylor
  2.     Drucker
  3.     McGregor
  4.     Galileo
 Discuss Question
Answer: Option D. ->  Galileo
Explanation :