Sail E0 Webinar

MCQs

Total Questions : 56 | Page 2 of 6 pages
Question 11. If an actual result is $5500 and corresponding amount of flexible budget on the basis of actual level of output is $3500, then flexible budget variance will be
  1.    $2,500
  2.    $5,500
  3.    $3,500
  4.    $2,000
 Discuss Question
Answer: Option D. -> $2,000
Answer: (d).$2,000
Question 12. The division of all the costs related to customers on the basis of different cost allocation bases or cost drivers are called
  1.    customer cost hierarchy
  2.    customer profitability hierarchy
  3.    treasury costing hierarchy
  4.    partial costing hierarchy
 Discuss Question
Answer: Option A. -> customer cost hierarchy
Answer: (a).customer cost hierarchy
Question 13. In customer cost hierarchy, the costs of all the incurred activities to sell a unit of product are classified as
  1.    customer sustaining costs
  2.    customer output unit-level costs
  3.    customer batch-level costs
  4.    corporate sustaining costs
 Discuss Question
Answer: Option B. -> customer output unit-level costs
Answer: (b).customer output unit-level costs
Question 14. Which of the following do not include among major categories of corporate costs?
  1.    human resource management costs
  2.    corporate administration costs
  3.    treasury costs
  4.    discretionary costs
 Discuss Question
Answer: Option D. -> discretionary costs
Answer: (d).discretionary costs
Question 15. If an actual result in static budget is $2500 and the corresponding budgeted amount is $2200, then the static budget variance will be
  1.    $3,000
  2.    $300
  3.    $4,700
  4.    $4,500
 Discuss Question
Answer: Option B. -> $300
Answer: (b).$300
Question 16. In customer cost hierarchy, the costs of those activities that cannot be traced to distribution channels or individual customers are called
  1.    discretionary channel costs
  2.    corporate-sustaining costs
  3.    distribution-channel costs
  4.    engineered resource costs
 Discuss Question
Answer: Option B. -> corporate-sustaining costs
Answer: (b).corporate-sustaining costs
Question 17. In customer cost hierarchy, the costs of individual customer support activities are classified as
  1.    discretionary channel costs
  2.    corporate-sustaining costs
  3.    distribution-channel costs
  4.    customer-sustaining costs
 Discuss Question
Answer: Option D. -> customer-sustaining costs
Answer: (d).customer-sustaining costs
Question 18. A joint cost allocation method is based on relative value of total sales, at the point of split off is classified as
  1.    sales value at split off method
  2.    joint costs at split off point method
  3.    joint products value at split off method
  4.    main product cost at split off method
 Discuss Question
Answer: Option A. -> sales value at split off method
Answer: (a).sales value at split off method
Question 19. The first step in constant gross margin percentage, Net realizable value (NRV) method is to allocate joint, to compute
  1.    Gross margin percentage
  2.    total production cost of each product
  3.    allocated joint costs
  4.    cost of split off point
 Discuss Question
Answer: Option A. -> Gross margin percentage
Answer: (a).Gross margin percentage
Question 20. In a joint process of production, the product which yields low volume of sales as compared to total sales of other products, specify as
  1.    Second incremental product
  2.    First incremental product
  3.    step down product
  4.    byproduct
 Discuss Question
Answer: Option D. -> byproduct
Answer: (d).byproduct

Latest Videos

Latest Test Papers