Reasoning Aptitude
CALENDAR MCQs
Total Questions : 60
Page 1 of 6 pages Answer is Option C. -> Thursday
Answer: (c) 4th Saturday = 22nd day 3rd Saturday = 22 - 7 = 15th day ∴ 13th day - Saturday - 2 = Thursday
Answer: (c) 4th Saturday = 22nd day 3rd Saturday = 22 - 7 = 15th day ∴ 13th day - Saturday - 2 = Thursday
Answer is Option C. -> Tuesday
Answer: (c) Here, 27th March 1995 was Monday. Now, for calculating the total number of odd days. first, we calculate the total number of days till 1 November 1994. ∴ Number of days in March, 1995 = 27 Number of days in February 1995 = 28 Number of days in January 1995 = 31 Number of days in December 1994 = 31 Number of days in November 1994 = 29 Total number of days = 146 ∴ Number of odd days = $146/7$ = 20$6/7$ So, 6 odd days ∴ On November 1, 1994 = Monday - 6 = Tuesday
Answer: (c) Here, 27th March 1995 was Monday. Now, for calculating the total number of odd days. first, we calculate the total number of days till 1 November 1994. ∴ Number of days in March, 1995 = 27 Number of days in February 1995 = 28 Number of days in January 1995 = 31 Number of days in December 1994 = 31 Number of days in November 1994 = 29 Total number of days = 146 ∴ Number of odd days = $146/7$ = 20$6/7$ So, 6 odd days ∴ On November 1, 1994 = Monday - 6 = Tuesday
Answer is Option B. -> Tuesday
Answer: (b) Tomorrow = Friday 3 days after tomorrow = 15th June = Friday + 3 odd days = Monday Days from 15th to 30th June = 15 15 ÷ 7 = 7)15(2 =>remainder 1 odd day 30th June = Monday + 1 odd day = Tuesday
Answer: (b) Tomorrow = Friday 3 days after tomorrow = 15th June = Friday + 3 odd days = Monday Days from 15th to 30th June = 15 15 ÷ 7 = 7)15(2 =>remainder 1 odd day 30th June = Monday + 1 odd day = Tuesday
Answer is Option D. -> Sunday
Answer: (d) Since Total days from 15th August, 2011 to 17 September, 2011 = 33 33 ÷ 7 => 7)33(4 = remainder 5 odd days ∴ Required day = Tuesday + 5 odd days = Sunday
Answer: (d) Since Total days from 15th August, 2011 to 17 September, 2011 = 33 33 ÷ 7 => 7)33(4 = remainder 5 odd days ∴ Required day = Tuesday + 5 odd days = Sunday
Answer is Option B. -> Monday
Answer: (b) 1st April 1901 means 1900 complete years + first 3 months of 1901 + 1 day of April Number of odd days in 1600 yrs = 0 Number of odd days in 300 yrs = 1 Number of odd days in 1901 yrs January 3 February 0 March 3 April 1 = 3 + 0 + 3 + 1 = 7 ⇒ 0 odd days Total number of odd days till 1st April 1901 = 0 + 1 + 0 = 1 So, the required day was Monday.
Answer: (b) 1st April 1901 means 1900 complete years + first 3 months of 1901 + 1 day of April Number of odd days in 1600 yrs = 0 Number of odd days in 300 yrs = 1 Number of odd days in 1901 yrs January 3 February 0 March 3 April 1 = 3 + 0 + 3 + 1 = 7 ⇒ 0 odd days Total number of odd days till 1st April 1901 = 0 + 1 + 0 = 1 So, the required day was Monday.
Answer is Option A. -> Monday
Answer: (a) 15th August 1949 means, 1948 complete year + First 7 months of the year 1949 + 15 days of August Number of odd days in 1600 yrs = 0 Number of odd days in 300 yrs = 1 Number of odd days in 48 yr (36 non - leap years + 12 leap years) = 36 × 1 + 12 × 2 = 60 = 7 × 8 + 4 = 4 odd days From 1st January 1949 to 15th August 1949 Number of odd days in 1949, January 3 February 0 March 3 April 2 May 3 June 2 July 3 August (15 ÷ 7) = 1 Total number of odd days in 1949 = 3 + 0 + 3 + 2 + 3 + 2 + 3 + 1 = 17 = 7 × 2 + 3 = 3 odd day Total odd days = 1 + 4 + 3 = 8 = 1 odd days Since, 1 is the code for Monday. Therefore, the required day was Monday.
Answer: (a) 15th August 1949 means, 1948 complete year + First 7 months of the year 1949 + 15 days of August Number of odd days in 1600 yrs = 0 Number of odd days in 300 yrs = 1 Number of odd days in 48 yr (36 non - leap years + 12 leap years) = 36 × 1 + 12 × 2 = 60 = 7 × 8 + 4 = 4 odd days From 1st January 1949 to 15th August 1949 Number of odd days in 1949, January 3 February 0 March 3 April 2 May 3 June 2 July 3 August (15 ÷ 7) = 1 Total number of odd days in 1949 = 3 + 0 + 3 + 2 + 3 + 2 + 3 + 1 = 17 = 7 × 2 + 3 = 3 odd day Total odd days = 1 + 4 + 3 = 8 = 1 odd days Since, 1 is the code for Monday. Therefore, the required day was Monday.
Answer is Option D. -> Wednesday
Answer: (d) 19th August 1992 means, 1991 complete years + First 7 months of 1992 + 19 days of August Number of odd days in 1600 years = 0 Number of odd days in 300 yrs = 1 Number of odd days in 91 yrs (22 leap year + 69 non-leap years) = 22 × 2 + 69 × 1 = 44 + 69 113 = 7 × 16 + 1 = 1 odd day From 1st January, 1992 to 19th August, 1992 Number of odd days in 1992, January 3 February 1 March 3 April 2 May 3 June 2 July 3 August 5 = 3 + 1 + 3 + 2 + 3 + 2 + 3 + 5 = 22 = 7 × 3 + 1 = 1 odd day ∴ Number of odd days till 19th August, 1992 = 0 + 1 + 1 + 1 = 3 So, the required day was Wednesday.
Answer: (d) 19th August 1992 means, 1991 complete years + First 7 months of 1992 + 19 days of August Number of odd days in 1600 years = 0 Number of odd days in 300 yrs = 1 Number of odd days in 91 yrs (22 leap year + 69 non-leap years) = 22 × 2 + 69 × 1 = 44 + 69 113 = 7 × 16 + 1 = 1 odd day From 1st January, 1992 to 19th August, 1992 Number of odd days in 1992, January 3 February 1 March 3 April 2 May 3 June 2 July 3 August 5 = 3 + 1 + 3 + 2 + 3 + 2 + 3 + 5 = 22 = 7 × 3 + 1 = 1 odd day ∴ Number of odd days till 19th August, 1992 = 0 + 1 + 1 + 1 = 3 So, the required day was Wednesday.
Answer is Option C. -> Monday
Answer: (c) 30th June 1980 means 1979 complete years + 6 months of 1980 Number of odd days in 1600 yrs = 0 Number of odd days in 300 yrs = 1 Number of odd days in 79 yrs = (19 leap yrs + 60 ordinary years) = 19 × 2 + 60 × 1 = 38 + 60 = 98 ⇒ o odd days January 3 February 1 March 3 April 2 May 3 June 2 Number of odd days in 1980 = 3 + 1 + 3 + 2 + 3 + 2 = 14 ⇒ 0 odd days Total number of odd days till 30th June, 1980 = 0 + 1 + 0 + 0 = 1 So, the required day was Monday.
Answer: (c) 30th June 1980 means 1979 complete years + 6 months of 1980 Number of odd days in 1600 yrs = 0 Number of odd days in 300 yrs = 1 Number of odd days in 79 yrs = (19 leap yrs + 60 ordinary years) = 19 × 2 + 60 × 1 = 38 + 60 = 98 ⇒ o odd days January 3 February 1 March 3 April 2 May 3 June 2 Number of odd days in 1980 = 3 + 1 + 3 + 2 + 3 + 2 = 14 ⇒ 0 odd days Total number of odd days till 30th June, 1980 = 0 + 1 + 0 + 0 = 1 So, the required day was Monday.
Answer is Option A. -> Wednesday
Answer: (a) 18th September 1991 means, 1990 complete years + 8 months of 1991 + 18 days of September Number of odd days in 1600 yrs = 0 Number of odd days in 300 yrs = 1 Number of odd days in 90 yrs (22 leap year + 68 ordinary years ) = 22 × 2 + 68 × 1 = 44 + 68 = 112 ⇒ 0 odd days Number of odd days in 1991, January 3 February 0 March 3 April 2 May 3 June 2 July 3 August 3 September 4 = 3 + 0 + 3 + 2 +3 + 2 + 3 + 3 + 4 = 23 = 7 × 3 + 2 = 2 odd days Total number of odd days till 18th September, 1991 = 0 + 1 + 0 + 2 = 3 So, the required day was Wednesday.
Answer: (a) 18th September 1991 means, 1990 complete years + 8 months of 1991 + 18 days of September Number of odd days in 1600 yrs = 0 Number of odd days in 300 yrs = 1 Number of odd days in 90 yrs (22 leap year + 68 ordinary years ) = 22 × 2 + 68 × 1 = 44 + 68 = 112 ⇒ 0 odd days Number of odd days in 1991, January 3 February 0 March 3 April 2 May 3 June 2 July 3 August 3 September 4 = 3 + 0 + 3 + 2 +3 + 2 + 3 + 3 + 4 = 23 = 7 × 3 + 2 = 2 odd days Total number of odd days till 18th September, 1991 = 0 + 1 + 0 + 2 = 3 So, the required day was Wednesday.
Answer is Option B. -> 1, 8, 15, 22, 29
Answer: (b) First of all, we have to find the day on 1st April, 2012 1st April 2012 means (2011 years 3 months and 1 day) Now, 2000 years have 0 odd days 11 years have (2 leap years and 9 ordinary years) = ( 2 × 2 + 9 × 1 ) odd days = (4 + 9) odd days = 13 = 6 odd days 3 months and 1 day January 31 February 29 March 31 April 1 = 92 days = 1 odd day Total number of odd days = ( 6 + 1 ) = 7 ⇒ 0 odd day Hence, it was Sunday on 1st April 2012. (1st Sunday). Subsequently, Sundays of the month were on 1st, 8th, 15nd, 22nd, and 29th.
Answer: (b) First of all, we have to find the day on 1st April, 2012 1st April 2012 means (2011 years 3 months and 1 day) Now, 2000 years have 0 odd days 11 years have (2 leap years and 9 ordinary years) = ( 2 × 2 + 9 × 1 ) odd days = (4 + 9) odd days = 13 = 6 odd days 3 months and 1 day January 31 February 29 March 31 April 1 = 92 days = 1 odd day Total number of odd days = ( 6 + 1 ) = 7 ⇒ 0 odd day Hence, it was Sunday on 1st April 2012. (1st Sunday). Subsequently, Sundays of the month were on 1st, 8th, 15nd, 22nd, and 29th.
Recent Questions
Q. Apache Bigtop Uses ___________ For Continuous Integration T....
Q. Corporates Have Benefited Tremendously 1)/ From The Governme....
Q. A Little Gush Of Gratitude
Q. Among The Following Which Layer Is Directly Apposed To The C....
Q. Metal Chloride That Is Hydrated Is
Q. A Steel Member Used In The Furnace Construction To Take The ....
Q. Which Of The Following Is not Among The Advantages Of H....
Q. He Killed The Enemy By His Sword.
Q. Main Circuit Board In A Computer Is...
Q. The Interpreter Of Indian Constitution Is-
Q. Rectify
Q. How Many 4d Orbitals Are There In An Atom?
Q. If You Increase The Mass On An Object, Its Acceleration
Q. Which Of The Following Is Capable Of Oxidizing Sulfur To Sul....
Q. An....
Q. India's First Private Sector Rocket Vikram-S, Was Developed ....
Q. Rover Weighs Less Than Fido. Rover Weighs More Than Boomer. ....
Q. A Cross Shaped (+) Or A Ring Involving Four Chromosomes May ....
Q. Priming Is Needed In A __________ Pump.
Q. Dynamic Similarity Is Said To Exist Between The Model And Th....