Which of the following is not a task performed under the ‘part development’ phase in the QFD process?
Options:
A .  Deployment of the QFD process down to sub-components level
B .  Deployment of the component deployment chart
C .  Relating the critical sub-component control characteristics
D .  Discovering customer requirements
Answer: Option D
Answer: (d).Discovering customer requirements