The value added manufacturing time is divided by total manufacturing, is to calculate
Options:
A .  value chain efficiency
B .  value chain effectivity
C .  manufacturing cycle effectivity
D .  manufacturing cycle efficiency
Answer: Option D
Answer: (d).manufacturing cycle efficiency