A .  If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed
B .  If the float of an activity is negative, delay in its performance is bound to delay the completion of project
C .  If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
D .  All of the above
Answer: Option D