Pick up the correct statement from the following:
Options:
A .  The difference of latest occurence time and earliest expected time, is called slack
B .  The activities connecting the events having zero slack, lie on the critical path
C .  The critical path consumes the maximum time
D .  All the above.
Answer: Option D
Answer: (d).All the above.