Sail E0 Webinar
Question
Pick up the correct statement from the following:
Options:
A .  The estimated value of the work excluding the amount for contingencies, work charged establishment, tool and plants, is called work value
B .  The actual expenditure involved to complete a work including incidental, establishment and travelling charges, is called actual cost
C .  The formal acceptance by the administrative department for incurring an expenditure on the work, is called administrative approval
D .  All the above
Answer: Option D

Submit Your Solution Below and Earn Points !
Next Question

Submit Solution