In testing a pile by load test, pile platform is loaded with one and half times the design load and a maximum settlement is noted. The load is gradually removed and the consequent rebound is measured. For a safe pile, the net settlement (i.e. total settlement minus rebound) per tonne of test load should not exceed
Options:
A .  10 mm
B .  15 mm
C .  20 mm
D .  25 mm
Answer: Option D