In a grit chamber of a sewage treatment plant,
Options:
A .  Flow velocity 0.15 m to 0.3 m/sec is kept
B .  Depth of 0.9 m to 1.20 m is kept
C .  One minute of detention period is kept
D .  All the above
Answer: Option D