If you are planning a project in SAP PS using CJ40 Work Breakdown Structure, at which of the following locations can you find the values used in the planning?
Options:
A .  RPSCO table
B .  COSS & COSP tables
C .  BPEJ table
D .  None of the mentioned
Answer: Option B