If the peak load on a power plant having a capacity of 100 MW is 70 MW during a given week and the energy produced is 58, 80,000 kWh, the capacity factor for the plant for the week will be ___________________
Options:
A .  35%
B .  50%
C .  70%
D .  65%
Answer: Option A
Answer: (a).35%