Question
If the peak load on a power plant having a capacity of 100 MW is 70 MW during a given week and the energy produced is 58, 80,000 kWh, the capacity factor for the plant for the week will be ___________________
Answer: Option A
Answer: (a).35%
Was this answer helpful ?
Answer: (a).35%