If the budgeted price of input is $50, actual quantity of input is 150 units and the allowed budgeted quantity of input is 60 units then efficiency variance will be
Options:
A .  $4,500
B .  $3,500
C .  $2,500
D .  $1,500
Answer: Option A
Answer: (a).$4,500