If only 2 workers were employed on this job on Day 4, what could be the minimum amount that Mr. Shyam pays the workers for this job for 6 days?
Options:
A .  Rs. 4000
B .  Rs. 2400
C .  Rs. 3680
D .  Rs. 3660
Answer: Option B
:
B
We get the following possibilities:
Day1Day2Day3Day4Day5Day6ManhrsRs.321234120240034323415230403232341362720

Was this answer helpful ?