How to set a deadline in MS project?
Options:
A .  Double-click a task -> it will open a task information dialog box
B .  Now, click on the advanced tab
C .  Then click on the arrow in the deadline field to show the calendar and then choose a date
D .  All of the above
Answer: Option D