For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is
Options:
A .  dry rolling, wet rolling, application of screening and application of filler
B .  dry rolling, application of filler, wet rolling and application of screening
C .  dry rolling, application of screening, wet rolling and application of filler
D .  dry rolling, application of screening, application of filler and wet rolling
Answer: Option C